Teploenergomontazh
JSC «Teploenergomontazh»
Assembling of heat and power equipment and rendering of services
Teploenergomontazh
JSC «Teploenergomontazh»
Assembling of heat and power equipment and rendering of services

Projects

CHPP in Sovetskaya Gavan , Теплоэнергомонтаж

CHPP in Sovetskaya Gavan

Russia Khabarovskiy krai

2015-2017

CHPP in Sovetskaya Gavan construction. Assembling of three steam boilers E-210-13.8-56KTC (model TPE-131).

Angren GRES Power Plant, Теплоэнергомонтаж

Angren GRES Power Plant

Uzbekistan

2008

Repair of the turbine (K-100)

Nadzhibia TPP, Теплоэнергомонтаж

Nadzhibia TPP

Iraq

2000-2002

Major repair of the two turbines and replacement of the four boilers.

TPP Harta, Теплоэнергомонтаж

TPP Harta

Iraq

2013-2014

Check-up and assembling of the feed water pumps. Technical assistance for turbine shop.

Razdan TPP, Теплоэнергомонтаж

Razdan TPP

Republic of Armenia

2009-2014

Assembling of the turbine, generator and auxiliary equipment (Unit 300 MW).

2014

Repair of the turbine (K-300-240-3).

Tazhiatash TPP, Теплоэнергомонтаж

Tazhiatash TPP

Uzbekistan

2007

Repair of the generator rotor (Unit 200 MW).

Talimarjan TPP, Теплоэнергомонтаж

Talimarjan TPP

Uzbekistan

1993-2004

Construction of the Talimarjan GRES Power Plant 800 MW.

2004-2009

Maintenance of the unit №1. Turbine and auxiliary equipment inspection.

2010

Maintenance of the unit №1. Turbine and auxiliary equipment inspection.

2011-2015

Repair of the main and auxiliary equipment (Unit №1).

GTPP «Etelebou», Теплоэнергомонтаж

GTPP «Etelebou»

Nigeria

2007-2008

Assembling of the three gas turbine power unit (the capacity of each 20 MW).

Tashkent TPP, Теплоэнергомонтаж

Tashkent TPP

Uzbekistan

2014-2015

Constriction of the “PGU-370” (CCPP). Main building. Assembling of the gas turbine, steam turbine, HRSG, exhaust stack, main and auxiliary equipment, high and low pressure pipelines, fuel gas preparation unit.

Syrdarya TPP, Теплоэнергомонтаж

Syrdarya TPP

Uzbekistan

2007-2008

Repair of the turbine (K-300-240). Technical assistance in repair.

NPP «Bushehr» , Теплоэнергомонтаж

NPP «Bushehr»

Islamic Republic of Iran

2003-2011

Assembling of the turbine unit (K-1000-60/3000-3).

2012

Assembling and renovation works of the turbine set (K-1000-60/3000-3)

2013

Repair of the turbine (K-1000-60/3000-3)

2014

Repair of the turbine (K-1000-60/3000-3) and main equipment

2015

Major repair of the turbine set (K-1000-60/3000-3) and the power generator unit (TVV-1000)

2016

Maintenance of the turbine set (K-1000-60/3000-3)

Reftinskaya GRES Power Plant, Теплоэнергомонтаж

Reftinskaya GRES Power Plant

Russia Sverdlovsk Region

2007-2008

Replacement of the generator (Unit №10, 500 MW).

Cherepetskaya GRES Power Plant, Теплоэнергомонтаж

Cherepetskaya GRES Power Plant

Russia Tula Region

2011

Assembling of the steam turbine (K-225-12.8-4R), main and auxiliary equipment, high and low pressure pipelines, firefighting water system and industrial sewage (Unit №8).

2012-2013

Assembling of the steam turbine with condenser, auxiliary equipment of turbine hall, turbine internal piping and generator (Unit №9). Additional work for installation of makeup water piping (Unit №8).

2014-2015

Assembling of high pressure pipelines (Unit №9). Assembling of turbine internal piping, generator and condenser (Unit №8).

Kaliningrad TPP-2, Теплоэнергомонтаж

Kaliningrad TPP-2

Russia Kaliningrad

2007

Replacement of a inlet air filter unit. Assembling of a heat transport system.

2008

Civil works, unit №2 (PGU-450).

2009

Major repair of the steam and gas turbines, generators and auxiliary equipment of the unit №1. Construction of service water system and refrigerating system of the cooling tower №2. Supply and assembling of circulation pipelines. Laying foundations for steam and gas turbines. Assembling of the steam turbine (PT-150-7.7) and auxiliary equipment (Unit №2).

2010-2011

Construction of the unit gas conditioning station, assembling of high and low pressure pipelines of unit №2. Renovation of the high pressure steam superheater of HRSG (P-96), water-treatment plant.

Nizhnevartovskaya GRES Power Plant, Теплоэнергомонтаж

Nizhnevartovskaya GRES Power Plant

Russia YNAD

2012-2014

Construction of the unit №3. Assembling of steam turbine, main and auxiliary equipment, high and low pressure pipelines and circulating pipelines.

Urengoyskaya GRES Power Plant, Теплоэнергомонтаж

Urengoyskaya GRES Power Plant

Russia YNAD

2010

PGU-450 (CCPP 450 MW) construction. Overhead cranes assembling. Laying foundations for gas turbines.

2011

Assembling of the steam turbine (K-160-7.5), main and auxiliary equipment, high and low pressure pipelines and in-plant gas pipelines.

2012-2013

Check-up of the low pressure piping valves of STP and GTP. Installation of metal structures in main building. Laying foundations for steam turbine.

2014

Repair of the generator (TZFP-160-2MUZ)

2015

Repair of the generator (TZFP-160-2MUZ)

Ivanovo GRES Power Plant (Ivanovskie PGU), Теплоэнергомонтаж

Ivanovo GRES Power Plant (Ivanovskie PGU)

Russia Ivanovo

2006

Assembling of heat and power equipment (Unit №1)

2007

Start-up and commissioning operations (Unit №1). Dismantling of civil structures in turbine shop.

2008

Main and auxiliary equipment assembling (Unit №2). Dismantling and assembling of the gas-turbine (GT №12). Repair of the condensed water storage tank, boiler pass, turbine-generator (GP-1) and steam turbine (PT-10).

2009

Assembling of auxiliary equipment and high pressure pipelines of delivery water and auxiliary steam (Unit №2).

2010-2011

Assembling of the steam turbine (K-110-6.5) and auxiliary equipment. Major repair the generator (TGF-110-2-UZ).

Vladimir CHPP-2, Теплоэнергомонтаж

Vladimir CHPP-2

Russia Vladimir

2012

Assembling of the steam turbine T-63/76-8.8, main and auxiliary equipment, high and low pressure pipelines and overhead cranes.

2013

Assembling of the turbine, metal structures and turbine operating floors.

2014

Vladimir CHPP-2 renovation.

CHPP-9 Mosenergo, Теплоэнергомонтаж

CHPP-9 Mosenergo

Russia Moscow

2007

Gas duct replacement.

CHPP-11 Mosenergo, Теплоэнергомонтаж

CHPP-11 Mosenergo

Russia Moscow

2007

Air inlet system repair (boiler №10).

CHPP-23 Mosenergo, Теплоэнергомонтаж

CHPP-23 Mosenergo

Russia Moscow

2007

Gas pipelines replacement.

Yaroslavl CHPP-1, Теплоэнергомонтаж

Yaroslavl CHPP-1

Russia Yaroslavl

2005

Rotor turning gear renovation.

2006

Thermal and mechanical equipment repair.

Sochi TPP, Теплоэнергомонтаж

Sochi TPP

Russia Sochi

2009

Assembling of HRSG, gas pipelines and gas turbines.

Uzhnaya CHPP-22, Теплоэнергомонтаж

Uzhnaya CHPP-22

Russia Saint Petersburg

2010

Assembling of the steam turbine (PT-150-7.7) and auxiliary equipment. High and low pressure pipelines assembling.

2011

Renovation of condensate purification plant and rotor turning gear.