07-10-2016, CHPP in Sovetskaya Gavan

Front curtain wall and platen superheater under assembling


07-10-2016, ТЭЦ в г. Советская Гавань

Preparation for assembling boiler drum of unit №2


07-10-2016, Tashkent TPP

Boiler acid cleaning is completed. There is a circuit restoration and preparing for blowdown. Steam turbine lube oil system washing is completed, half-coupling is coupled.


07-10-2016, NPP Bushehr

Carry out preparation work for technical maintenance of turbine K-1000.Repair is planning for January 2017


01-10-2016, Talimarjan TPP

Technical maintenance of steam turbine K-800-240 is completed. Vibratory condition of the turbine is acceptable.


03-10-2016, CHPP in Sovetskaya Gavan

Front curtain wall of unit №2 is assembled.